Downtime in CNC production? Not with KELLER! (Customer Case Study)

Stuck with a tricky machining job and no solution in sight? One of our customers recently faced the same challenge…

❓The Problem:
Their CNC control system couldn’t handle two opposing 3-start flat threads on a stretch roller (Ø152, length approx. 3m). A costly delay seemed inevitable.

💡The Solution:
With SYMplus™, they got back on track—fast! A custom macro allowed them to rough and finish the threads using standard grooving tools in multiple small passes. No downtime, no hassle—just smooth production.

  • Got a machining challenge of your own? Let’s solve it together!

Do you have any questions?

Our experts are at your disposal. We look forward to your inquiry!

Klaus Reckermann

    Mr.Ms.